Please ensure Javascript is enabled for purposes of website accessibility

Project Overview

The CTH U Reconstruction Project will improve safety, mobility, and infrastructure within the Village of Biron. The project includes roadway reconstruction, stormwater system upgrades for improved drainage, utility improvements, and recreational trail extension.

Project Updates

Week of November 9th, 2026

Current Work

  • Crews completed the storm sewer installation yesterday and are now continuing roadway grading in preparation for asphalt paving.
  • Central Staking is scheduled to be onsite today to complete the necessary staking for upcoming concrete and asphalt work.
  • Sommers is scheduled to be onsite Friday and Monday to continue concrete work, including curb installation.

Traffic Impacts

  • CTH U remains closed to traffic between South Biron Drive and Beaver Street.
  • ND Paper mill traffic is now permitted to cross North Biron Drive at Beaver Street to access the administration parking lot.
  • ND Paper traffic will otherwise continue to use the detour route of North Biron Drive to Short Street to Center Street, to Badger Street, to North Biron Drive, and to Beaver Street.
  • Head Start traffic will use the detour route of North Biron Drive to Short Street to Center Street to Badger Street to Williams Street access the back of the building for parking as needed.
  • All other traffic shall continue using posted detour route out to Huffman Road until otherwise noted.
  • Pedestrians are encouraged to use the designated temporary walkway and follow all posted signage.
  • Motorists are encouraged to follow all posted signage and traffic control devices.
  • Temporary traffic control devices have been installed along North Biron Drive until roadside safety features are restored.

Construction Progress

  • Storm sewer installation has been completed, with crews now focused on grading the roadway in preparation for asphalt paving.
  • Central Staking will be onsite today to complete staking for upcoming concrete and asphalt work.
  • Sommers is scheduled to pour curb on Friday and Monday as concrete work continues.
  • Roadway grading and preparation will continue throughout the week as crews work toward the next phase of construction.

View All Updates

Project Schedule

Project Design & Engineering                                                                              Complete

Roadway Reconstruction and Utility Upgrades (Phase 1)                  June - August

Roadway Reconstruction and Utility Upgrades (Phase 2)                  August - November

Roadway Reconstruction and Utility Relocation (Phase 3)               May 2027 – June 2027

Paving & Finishing (Phase 1&2)                                                                           October – November

Paving & Finishing (Phase 3)                                                                                  May 2027 - June 2027

Restoration (Phase 1&2)                                                                                          October - November

Restoration (Phase3)                                                                                                May 2027 - June 2027

View Full Schedule

 

Frequently Asked Questions

Phase 1 and 2 of the project is expected to be completed in Fall 2026. Phase 3 of the project is expected to be compelted in early Summer 2027. Construction schedules may change due to weather, site conditions, or other unforeseen circumstances. Please check back regularly for weekly project updates and the latest construction schedule information.

Yes. Temporary restrictions may occur during specific phases of construction, but advance notice will be provided whenever possible.

Mail delivery may be temporarily impacted during construction. A mailbox cluster will be provided on Huffman Road, where residents can pick up their mail during the project. Residents are encouraged to use the mailbox cluster location for mail access while construction activities are occurring. Updates will be provided if there are any changes to mail delivery arrangements.

Updates will be posted weekly, typically every Wednesday. The Village receives the latest construction information during weekly project meetings held each Tuesday at 2:00 PM with the contractor and project team. Following those meetings, project updates will be prepared and posted to this page to keep residents informed of construction progress, upcoming work activities, traffic impacts, and any schedule changes.

This project has four primary points of contact:

The WisDOT Project Manager oversees the project on behalf of the Wisconsin Department of Transportation and serves as the primary project representative. The Contract Manager coordinates day-to-day construction activities and field operations. The Project Engineer is available to answer technical and design-related questions regarding the project. The Wood County Highway Commissioner provides oversight and coordination on behalf of Wood County Highway Department.