Project Overview

The CTH U Reconstruction Project will improve safety, mobility, and infrastructure within the Village of Biron. The project includes roadway reconstruction, stormwater system upgrades for improved drainage, utility improvements, and recreational trail extension.

Project Updates

Week of October 19th, 2026

Current Work

  • Crews have completed all watermain installation in Phases 1 and 2.
  • Crews are working on storm sewer installation at the intersection of Bear Street and North Biron Drive and will continue working east.
  • Grading operations will follow storm sewer installation as crews complete each section.
  • Crews will continue finish grading in preparation for asphalt paving.
  • Potholes along the roadway between Short Street and Huffman Road will be filled prior to winter.

Traffic Impacts

  • CTH U remains closed to traffic between South Biron Drive and Beaver Street.
  • ND Paper traffic will continue to use the detour route of North Biron Drive to Short Street to Center Street, to Badger Street, to North Biron Drive, and to Beaver Street.
  • Head Start traffic will use the detour route of North Biron Drive to Short Street to Center Street to Badger Street to Williams Street access the back of the building for parking as needed.
  • All other traffic shall continue using posted detour route out to Huffman Road until otherwise noted.
  • Pedestrians are encouraged to use the designated temporary walkway and follow all posted signage.
  • Motorists are encouraged to follow all posted signage and traffic control devices.
  • Temporary traffic control devices have been installed along North Biron Drive until roadside safety features are restored.

Construction Progress

  • Watermain installation has been completed in Phases 1 and 2.
  • Storm sewer installation is underway at the intersection of Bear Street and North Biron Drive, with work progressing east.
  • Grading will continue behind storm sewer installation as crews complete each section.
  • Finish grading will be completed in preparation for asphalt paving.
  • Potholes between Short Street and Huffman Road will be filled prior to winter.

View All Updates

Project Schedule

Project Design & Engineering                                                                              Complete

Roadway Reconstruction and Utility Upgrades (Stage 1)                  June - August

Roadway Reconstruction and Utility Upgrades (Stage 2)                  August - September

Roadway Reconstruction and Utility Relocation (Stage 3)               September - October

Paving & Finishing                                                                                                      October - November

Restoration                                                                                                                     November

View Full Schedule

 

Frequently Asked Questions

The project is expected to be completed in Fall 2026. Construction schedules may change due to weather, site conditions, or other unforeseen circumstances. Please check back regularly for weekly project updates and the latest construction schedule information.

Yes. Temporary restrictions may occur during specific phases of construction, but advance notice will be provided whenever possible.

Mail delivery may be temporarily impacted during construction. A mailbox cluster will be provided on Huffman Road, where residents can pick up their mail during the project. Residents are encouraged to use the mailbox cluster location for mail access while construction activities are occurring. Updates will be provided if there are any changes to mail delivery arrangements.

Updates will be posted weekly, typically every Wednesday. The Village receives the latest construction information during weekly project meetings held each Tuesday at 2:00 PM with the contractor and project team. Following those meetings, project updates will be prepared and posted to this page to keep residents informed of construction progress, upcoming work activities, traffic impacts, and any schedule changes.

This project has four primary points of contact:

The WisDOT Project Manager oversees the project on behalf of the Wisconsin Department of Transportation and serves as the primary project representative. The Contract Manager coordinates day-to-day construction activities and field operations. The Project Engineer is available to answer technical and design-related questions regarding the project. The Wood County Highway Commissioner provides oversight and coordination on behalf of Wood County Highway Department.