Please ensure Javascript is enabled for purposes of website accessibility

Project Overview

The CTH U Reconstruction Project will improve safety, mobility, and infrastructure within the Village of Biron. The project includes roadway reconstruction, stormwater system upgrades for improved drainage, utility improvements, and recreational trail extension.

Project Updates

Week of June 22nd, 2026

Current Work

  • Segment 1 saw cutting operations and installation of temporary asphalt pedestrian pathways are underway between South Biron Drive and Badger Street.
  • Additional barricades and pedestrian traffic control measures will be installed upon completion of the temporary pathways.
  • Contractor mobilization and site preparation activities continue throughout Segment 1.

Traffic Impacts

  • CTH U remains closed to through traffic between South Biron Drive and Badger Street.
  • The posted detour route remains in effect.
  • Motorists are encouraged to follow all posted signage and traffic control devices.

Construction Progress

  • Segment 1 construction activities remain on schedule.
  • Preparations are underway for the next phase of utility installation work.

View All Updates

Project Schedule

Project Design & Engineering                                                                              Complete

Roadway Reconstruction and Utility Upgrades (Stage 1)                  June - August

Roadway Reconstruction and Utility Upgrades (Stage 2)                  August - September

Roadway Reconstruction and Utility Relocation (Stage 3)               September - October

Paving & Finishing                                                                                                      October - November

Restoration                                                                                                                     November

View Full Schedule

 

Frequently Asked Questions

The project is expected to be completed in Fall 2026. Construction schedules may change due to weather, site conditions, or other unforeseen circumstances. Please check back regularly for weekly project updates and the latest construction schedule information.

Yes. Temporary restrictions may occur during specific phases of construction, but advance notice will be provided whenever possible.

Mail delivery may be temporarily impacted during construction. A mailbox cluster will be provided on Huffman Road, where residents can pick up their mail during the project. Residents are encouraged to use the mailbox cluster location for mail access while construction activities are occurring. Updates will be provided if there are any changes to mail delivery arrangements.

Updates will be posted weekly, typically every Wednesday. The Village receives the latest construction information during weekly project meetings held each Tuesday at 2:00 PM with the contractor and project team. Following those meetings, project updates will be prepared and posted to this page to keep residents informed of construction progress, upcoming work activities, traffic impacts, and any schedule changes.

This project has four primary points of contact:

The WisDOT Project Manager oversees the project on behalf of the Wisconsin Department of Transportation and serves as the primary project representative. The Contract Manager coordinates day-to-day construction activities and field operations. The Project Engineer is available to answer technical and design-related questions regarding the project. The Wood County Highway Commissioner provides oversight and coordination on behalf of Wood County Highway Department.